The Nigerian Upstream Petroleum Regulatory Commission (NUPRC) has set the first quarter of 2027 as the new target for completing its proposed headquarters in Abuja, saying the facility could strengthen Nigeria’s appeal to international oil and gas investors.
The 10-storey building, known as The Barrel, is being constructed in Abuja’s Central Business District. It was initiated in 2020 and is designed to accommodate between 900 and 1,000 people.
Read Also:
The project remains incomplete, leaving the upstream regulator operating from multiple smaller offices across the Federal Capital Territory.
During an inspection of the project, NUPRC Board Chairman, Senator Magnus Abe, said the Commission’s fragmented office arrangement could hurt Nigeria’s investment image, particularly when major international oil companies visit the country to discuss multibillion-dollar projects.
“It is a thing of great embarrassment to this country when major oil and gas companies come to Nigeria to discuss investments worth billions of dollars, only to meet the regulator in a block of flats and from there proceed to other parts of the city to see different departments to conduct transactions with the NUPRC,” Abe said.
“This image is not just bad for the country, but bad for business.”
NUPRC wants the barrel to become a central hub for its regulatory operations and engagements with oil and gas companies.
The Commission says consolidating its departments in one location would make interactions with industry stakeholders more efficient while giving the regulator a more visible institutional presence.
For an industry that depends heavily on long-term capital commitments, the physical infrastructure surrounding regulation can also influence how investors perceive the efficiency and stability of the operating environment.
Abe said the completed facility would provide a central location for the Commission and serve as a symbol of confidence in Nigeria’s upstream petroleum sector.
The project is being constructed by Julius Berger Nigeria Plc.
NUPRC Chief Executive, Oritsemeyiwa Eyesan, directed the contractor to accelerate construction and deliver the project by the first quarter of 2027.
Julius Berger Nigeria Managing Director, Peer Lubasch, said the company would make efforts to meet the deadline.
Abe said recent government policies were already contributing to renewed investment in the sector, with the resulting projects creating employment, generating business opportunities and supporting development in host communities.
NUPRC has been pursuing measures aimed at increasing upstream activity and attracting fresh capital. Earlier in July, the regulator directed new Petroleum Prospecting Licence holders to accelerate development of their assets under the Petroleum Industry Act’s “drill or drop” provisions as Nigeria targets higher crude production.
The Commission has also said it expects major offshore projects between 2026 and 2030 to attract substantial investment into Nigeria’s upstream sector.
For NUPRC, completing The Barrel is therefore being positioned as more than an office relocation.
The regulator wants the building to centralise its operations, improve engagement with oil companies and present a more organised face to investors considering Nigeria’s upstream sector.